Implementing SMED
In my last blog ( "SMED Explanation
" - Link :
https://kalpanathchatterjee.blogspot.com/2019/03/smed-explanation.html), I have already detailed that Japanese
Industrial Engineer Shigeo Shingo gave birth to the concept of SMED by helping
companies dramatically reduce their setup change over time. With his concepts
he was able to bring down the changeover times averaging 94% as
documented.
It may be hard to imagine that the change
over time have improvement by a factor of approximately 20. E.g - setup time of
90 minutes have been brought down to 5 minutes across the wide range of
companies.
There are two types of work element
category, i.e. Internal Element and External Element.
- Internal Element: Work elements that can be performed only when the machine / equipment is completely stopped.
- External Element: Work elements that can be performed even if the machine / equipment is running.
An Industrial Engineer must not assume,
or must not take decision based upon one single Setup change trial. If possible
video graphing of the setup/ changeover may be done during dry-run of the
changing over process for at least five setup/ change overs. Time recording
must be done for each of the work elements. Outlier conditions must be
critically observed. Focused problem solving along with team brain storming
must be the approach along with no-cost or low cost automation.Clear separation
of Internal and external work elements must be done. Following figure explains
the external and internal element separation exercise:
- How to Select an SMED Project Pilot Area?
It has been detailed in my earlier blog (link: https://kalpanathchatterjee.blogspot.com/2019/03/smed-explanation.html)
that SMED targets that
the changeover process must get completed in less than 10 minutes ( Single
Digit Minute). It is always better to go for SMED implementation at Pilot
Machine at the initial phase of understanding building. In order to have better
results project team must include complete spectrum of employees associated
with machine/ equipment. The pilot area for SMED program depends on
selection of ideal equipment having following characteristics:
S. No.
|
Characteristics
|
Description of relevance
|
1.
|
Duration
of Changeover
|
The changeover should be long enough to have significant
room for improvement. E.g. Approximately one hour implementation time may be
able to present a good amount of room for SMED implementation.
|
2.
|
Variation
in changeover time
|
If there is presence of large variations in
changeover time, (i.e. Changeover time variation ranges from one to three
hours), than the machine should be selected to run pilot project.
|
3.
|
Opportunities
for testing
|
If
the frequency of changeover is high (approximately thrice in a week) then the
implemented improvements done in SMED project can be easily tested.
|
4.
|
Familiarity
with the machine/ equipment
|
The
project team must be familiar with the machine / equipment selected to run
pilot project.
|
5.
|
Constraint
analysis
|
If
the equipment is a bottleneck in the process then improvement project must be
conducted on it. Changeover time reduction will help in line balancing as
well.
|
Once the equipment is selected, to begin with, the
project execution team must follow the conventional way of conducting SMED
Implementation. Figure below describes the complete set of processes:
The detailed Seven stages of SMED is described in
the following links:
1.
Document the setup/changeover and separate the work elements in to internal and external Elements (Link : Step 1 of SMED Implementation)
2.
Standardize external setup activities (Link : Step 2 of SMED Implementation)
3.
Convert internal setup activities to external
setup activities (Link: Step 3 of SMED Implementation)
4.
Improve internal changeover tasks ( Link : Step 4 of SMED Implementation )
5.
Improve external setup tasks (Link: Step 5 of SMED Implementation)
6.
Mechanizing the setup or using automation (Link : Step-6 of SMED Implementation)
7.
Complete elimination of changeover -Ideal
Situation (Link: Stepn7 of SMED Implementation)
To be continued…